NW 23rd Reconstruction Project
Why This Project?
- NW 23rd Avenue needs to be repaired and repaved.
The street shows severe cracking, rutting and potholes. In
places, the asphalt has worn down enough to expose the old
streetcar tracks and bricks.
- The roadway improvements are necessary to ensure access and
maintain the vitality of the neighborhood. Reconstruction
between the existing curbs will allow for a 20-plus year life
span of the pavement.
What Work Will Be Done?
- The project’s boundaries extend along NW 23rd
from Burnside to Lovejoy.
- The project will excavate the existing roadway, reconstruct
the base, and repave the surface.
- The project will install underground stormwater quality
vaults to capture pollutants and sediments before the
stormwater goes into the combined sewer system, which during
major rainstorms directs water into the Willamette River.
- The project will also install curb ramps on corners where
they are needed and rebuild existing ones to meet new
Americans with Disabilities Act (ADA) standards.
- Additional items of work may be included in the project
depending on feasibility and available funding. Project
planning will provide the time and resources to identify and
evaluate additional work.
- Click here for information on Planning
How Much Will The
Project Cost?
The latest engineer's estimate for the NW 23rd Reconstruction
Project is $2.654 million. We currently have a budget of $1.828
million - this includes $1.641 million of Federal transportation
funds and $187,820 in Portland General Transportation Revenues (GTR).
In order to do the basic reconstruction project, we estimate
that we need an additional $826,000 in funds. We are currently
exploring options for reducing project costs and have hired a
consultant to do a more thorough study of the condition of the
pavement.
The project was initially planned for work along NW 23rd
from Burnside to Lovejoy. However, the project’s budget will not
be able to cover the costs for this length. We estimate that we
will be able to complete work along four to six blocks from
Burnside to Glisan, Hoyt or Irving Streets.
We currently have a budget of $1.828 million - this includes
$1.641 million of Federal transportation funds and $187,820 in
Portland General Transportation Revenues (GTR).
PDOT will come back at a future date when funds are available
to complete the project to Lovejoy Street.
At the request of the NW District Association and the Nob Hill
Business Association, PDOT is delaying construction until 2006
- Project planning began in April 2005 and should be completed
in August 2005.
- The survey was completed at the end of January 2005.
- Preliminary engineering should begin in June 2005
- Construction is scheduled to begin in early 2006
- The project construction length will be determined during
preliminary engineering and can vary depending on how the
project is staged.
Project planning began in April 2005. A stakeholder advisory
committee (SAC) was formed with representatives from the
community, businesses, the Northwest District Association and the
Nob Hill Business association. They are working with Portland
Office of Transporation (PDOT) staff to identify and prioritize
project improvements within the current budget constraints. A
list of improvements outside the project budget are also being
developed for future implementation when funding becomes
available.
SAC Meeting Schedule
- April 11, 2005 Meeting
Summary
SAC List
SAC Schedule and
Process Diagram
- May 19, 2005 Meeting
Summary
SAC List
SAC Schedule and Process Revised
- June 15, 2005 Meeting
Summary
Staging and Traffic Control Scenarios
Conditions of Approval 24th Place Condominiums NW Westover and
Everett
- July 20, 2005 Good Sam Medical Bldg., 1140 NW 22nd
Avenue, 2nd Floor, 5-7pm
- August 24, 2005 Good Sam Medical Bldg., 1140 NW 22nd
Avenue, 1st Floor North-South Conference Room, 5-7pm
Click on a highlighted meeting date above for the meeting
summary and handouts. All meetings are open to the public.
Neighborhood residents and business owners
are key to the success of the project. Project staff will work
with the community, the NW District Association and the Nob Hill
Business Association to plan the project.
Construction is scheduled to begin in early 2006. The
construction length will be determined during preliminary
engineering and can vary depending on how the project is staged.
Project updates will posted on the web site during construction
If you have questions about the project or issues that should
be addressed, please contact:
Jean Senechal Biggs, Project Manager
Portland Office of Transportation
1120 SW 5th Ave, Suite 800
Portland, OR 97204
Phone: 503-823-7211
e-mail: jean.senechal@pdxtrans.org